The following is a list of state required inspections that apply to all new and additions to commercial and residential construction projects. Existing residential and commercial renovations will require some, if not all of the required inspections. For information pertaining to your specific project or to schedule an inspection, please contact the inspector listed on the front of your building, plumbing or mechanical permit. For additional contact information, a complete list of BCI inspectors and their phone numbers can be access by clicking this link.
For general information and questions pertaining to the inspection process:
General Building Inspections (GBI) 352-3267
Mechanical Inspection (MI) 352-3781
Plumbing Inspections (PI) 352-3280
Minimum Required Inspections
Soil Inspection
•Where a declaration of contract with a Geotechnical Engineer is not required, contact the GBI inspector to schedule the inspection.
•Electrical Inspection for grounding should be scheduled at this time Inspection Bureau Incorporated phone number is 381-6080
Foundation Inspection
•When reinforcing steel is listed on the approved plan as required, an inspection shall be preformed to verify its placement. Contact the GBI inspector to schedule the inspection.
Basement Slab Inspection
•Prior to placing concrete in the lowest level of the structure, it will be necessary to call for a sub-grade and vapor barrier inspection. Contact the GBI inspector to schedule the inspection.
•Plumbing Inspection and test of the under slab piping is required prior to slab placement. Contact the Plumbing Inspector between 7:00 and 8:30 AM for same day inspection.
Framing Inspection and initial Fire Stop Inspection
•Mechanical, Plumbing and Electrical rough inspections are required prior to scheduling the Framing Inspection. Please contact the appropriate section to schedule theses inspections.
•A Framing Inspection shall be preformed after the rough Mechanical, Plumbing and Electrical inspections have been approved. Contact the GBI inspector to schedule the inspection.
Insulation Inspection and balance of Fire Stop Inspection
•Inspection shall be preformed just prior to drywall installation. Contact the GBI inspector to schedule the inspection.
Final Inspection
•Final inspection will consist of final inspection approval from the following sections: Plumbing, Electric (Inspection Bureau Inc.) and Mechanical. In addition to those final approvals the General building inspector will verify that substantial compliance with the approved building permit plan has been achieved. Exterior site conditions will also be verified at this time.
Certificate of Occupancy
•A certificate of occupancy will be issued upon all final inspections being approved.
• In the event that occupancy is requested prior to all work being completed, a temporary conditional occupancy can be applied for under the following conditions.
•98% completion certificate received from IBI.
•Plumbing final preformed with the minimum fixtures in place.
•HVAC completed to minimum code compliance standards.
•Final grades with adequate erosion controls in place.
•Minimum required safety standards have been met.
Note: Initial temporary CO’s will be issued for a maximum of 90 days and thereafter are renewable every 30 days